Everything here is free. Making it takes time and money. Everything here is free.

Buy us a coffee

Trade job forms · TJ-22

Heat Pump Commissioning Record

A free printable heat pump commissioning sheet — the system as installed, design figures beside the readings taken, pre-start checks and the handover.

First page of the Heat Pump Commissioning Record — Put the designer's figure and your reading on the same line. The record then shows not just what the system was set to but whether that was what it was meant to be.
Download Free · no sign-up

One page. Choose your paper size — both versions are laid out identically, so neither one gets shrunk to fit.

Print it and write on it

Fill it in type and save

The fillable versions have real form fields — open them in any PDF reader, type into them and save. Printing help.

What this sheet is for

Put the designer's figure and your reading on the same line. The record then shows not just what the system was set to but whether that was what it was meant to be.

Who it is for

Heat pump installers and commissioning engineers, and heating firms taking on their first air-source or ground-source jobs.

How to use it

  1. Identify the unit, cylinder, buffer and emitters from their plates and the design document.
  2. For each setting, write the designer's or manufacturer's figure first, then what you set or read, and where you read it.
  3. Tick the pre-start checks as they are done; cross through any that do not apply to this system.
  4. Walk the customer through the controller, note the guarantee and scheme registrations, and have them sign.

What is on the sheet

One page, top to bottom:

Printed under the title: The day a heat pump goes live: the system as installed, the design figures beside the readings, and the handover.

Their figure beside your reading. Flow temperature, flow rate, glycol strength, clearances and the compensation curve are the designer's and the manufacturer's figures for this installation. Each gets two blanks — their figure and your reading — because a record with only the readings cannot show whether they were right.

Write-on lines: Customer · Address · Date · Commissioned by · Unit make & model · Serial no. · Type · Cylinder make & size · Emitters · Design ref

Settings and readings — their figure first, yours beside it

Table, 5 rows: Item · Whose figure · Their figure · Set to or read · Read where · Note

Before start-up and at handover — tick when done; cross through if not applicable

  • System flushed and cleaned before connection
  • Inhibitor or antifreeze added per the manufacturer
  • Outdoor unit clearances per the manufacturer
  • Condensate route and drain checked for freezing
  • Sensors in place and reading; clock set
  • Controller explained; customer can adjust it
  • Guarantee registered; scheme or grant notified
  • Handbooks, design pack and cert. no. left

Signature strip: Customer signature · Print name · Engineer

Questions

Why does the sheet not say what the flow temperature should be?

Because it is different for every house: it comes from the heat loss calculation, the emitters fitted and the unit's own range. The sheet gives that figure a column of its own so it is written down beside the reading, and the two can be compared later by someone who was not there.

Is this the same as the manufacturer's commissioning checklist?

No, and it does not replace it. The manufacturer's form proves the unit was set up as they require and usually matters for the guarantee. This is the installer's own record of the whole system, kept with the job file.

Related sheets

Heating Engineer Service Visit Sheet

Leave a visit record that stands on its own. It shows what was read, what was done about it, and what the customer was told before the van pulled away.

TJ-23 1 page

Boiler Service Record

Keep the proof of annual servicing that boiler warranties commonly ask for, and an index of which engineer did what.

HS-01 2 pages

Water Heater Maintenance Log

Track the two jobs that decide how long a water heater lasts: flushing out sediment and replacing the sacrificial anode before it is gone.

HS-02 2 pages

Job Completion and Sign-Off Form

Get the customer's signature that the work is done while you are still standing there, with anything outstanding written down rather than remembered differently.

IM-14 2 pages

Also in the resources library

The same subject, with a version you can fill in on screen.

Everything here is free

Every sheet, binder, game and puzzle on Upkeep Papers is free to download, with no email and no account. Making them is not free: each one takes days of research, design and checking, and the site costs money to run. If something here saved you time, you can buy us a coffee. It is entirely optional: nothing is locked, and nothing changes if you don’t.

Buy us a coffee

Opens PayPal in a new tab. Any amount, and nothing changes if you would rather not.